Buying a Turkish Apartment Without an Occupancy Permit: Which Transactions Are Blocked (Zoning Act Arts. 30-31)

A missing occupancy permit does not stop the sale and does not by itself make the building unlawful.

Av. Onur ÇalışıcıPublished 9 September 2026 · Updated 19 October 2026 · 14 min read
Engraving: a closed barrier in front of an apartment building, with a brass key before the barrier and a Turkish tea set at the side.

In brief

  1. The occupancy permit (yapı kullanma izni) is mandatory before a completed building or a completed part of it may be used, and it is issued only once the administration establishes that the building conforms to the permit and its annexes and that there is no technical objection to its use (Article 30, Zoning Law No. 3194).
  2. The single hardest consequence is registral: freehold condominium ownership (kat mülkiyeti) cannot be established without the occupancy permit, because Article 12(a) of Condominium Law No. 634 lists it among the documents that must be filed.
  3. Article 31 withholds electricity, water and sewerage from buildings with no permit, but the next sentence of the same article restores them for independent units that have obtained one, so a partial permit is a real remedy for an individual apartment.
  4. A missing permit and an unlawful building are two different things. Sealing, the annotation in the declarations column of the title register within seven days, and demolition all belong to Article 32, which applies to construction carried out without a permit or contrary to it, not to an otherwise compliant building whose paperwork was never collected.
  5. Where the shortfall was not disclosed, it is a legal defect in the sense of Article 219 of Turkish Code of Obligations No. 6098 and Article 8/2 of Consumer Protection Law No. 6502. Article 244/3 of Law No. 6098 gives five years from the transfer of ownership, and twenty where the seller is grossly at fault; for a consumer buying a home, Article 12/1 of Law No. 6502 gives five years from delivery and Article 12/3 disapplies limitation entirely where the defect was concealed by gross fault or fraud.

What it freezes is a specific list: the conversion of a construction servitude into freehold condominium ownership, the ex officio change of the property's registered class, and the utility connections of the units that lack it. This guide separates the administrative consequences from the myths and shows where the shortfall turns into a defect claim.

In Türkiye an apartment with no occupancy permit (yapı kullanma izni, commonly “iskân”) can still be sold, but three things cannot be done: freehold condominium ownership (kat mülkiyeti) cannot be established, because Article 12(a) of Condominium Law No. 634 lists the permit among the documents to be filed with the land registry; the property’s registered class is not changed ex officio; and under Article 31 of Zoning Law No. 3194 the building is not supplied with electricity, water and sewerage until the permit is obtained, although independent units that hold a permit are supplied. The municipality or governorate must decide a permit application within 30 days under Article 30, failing which use is deemed permitted. A building erected in conformity with a construction permit obtained by 1 July 2022 (for buildings constructed before 31 December 2021 the permit condition does not apply) may receive a temporary water and electricity connection under Provisional Article 11 of the same Law, which creates no acquired right.

A missing occupancy permit in Türkiye does not stop you buying the apartment, and it does not by itself make the building unlawful. What it stops is a short, specific list of transactions: the conversion of a construction servitude into freehold condominium ownership, the ex officio change of the property’s registered class, and, for the units that lack it, the electricity, water and sewerage connections. Everything else that is commonly said about the yapı kullanma izni is either a consequence of those three, or is not in the legislation at all. This guide separates them, reading Articles 30 to 32 of Zoning Law No. 3194 alongside Articles 3, 10, 12 and 14 of Condominium Law No. 634. The position is stated as at October 2026.

A ribboned title deed locked with a red padlock in front of an apartment block, with a lowered barrier before it.
Without an occupancy permit, some transactions on the apartment are blocked.

What is an occupancy permit (yapı kullanma izni) in Türkiye?

Article 30 of Law No. 3194 sets a use prohibition, not a formality. Where a building is completely finished, permission is required for the whole of it; where parts capable of separate use are finished, permission is required for those parts. The application is made by the owner, and the administration that issued the construction permit, the municipality or the governorate, must establish two things before granting it: that the building conforms to the permit and its annexes, and that there is no technical objection to its use.

Two features of the article are usually missed. The first is a deadline running against the administration: municipalities and governorates must conclude an owner’s application within thirty days, failing which use of the building, or of the finished part, is deemed permitted at the end of that period. The second is the sentence that closes the article, and it cuts the other way: a permit granted under Article 30 does not release the owner from liability arising out of failure to comply with the Law and with the permit and its annexes, nor from any obligation to pay taxes, duties and fees. The occupancy permit is a use authorisation. It is not an amnesty, and it is not a certificate of legality.

Article 31 then supplies the definition that drives most of the commercial consequences: the completion date of the construction is the date the use permit is granted. Until that date, in the eyes of the zoning legislation, the building is not finished, however habitable it looks.

Which transactions are blocked without an occupancy permit?

The blocked list is short and it is registral before it is practical.

TransactionPosition without an occupancy permitSource
Sale and transfer of title of the unitNot blocked. A construction servitude over a land share is transferred in the ordinary way, together with the land shareLaw No. 634, Arts. 14 and 5
Establishing freehold condominium ownership (kat mülkiyeti)Blocked. The occupancy permit is one of the documents that must be filed with the land registryLaw No. 634, Art. 12(a)
Converting an existing construction servitude into freehold ownershipBlocked. Conversion is ex officio, but only on the basis of the permit issued for the whole buildingLaw No. 634, Art. 3/3 and 10/6
Change of the registered class of the property (cins değişikliği)Blocked. The ex officio procedure is triggered by the permit being uploaded to the Spatial Address Registration System and sent to the cadastre officeLaw No. 634, Art. 10/6
Electricity, water and sewerage in the unit's own nameBlocked for units without a permit; available for units that have oneLaw No. 3194, Art. 31
Curing the position for your apartment aloneNot possible. Freehold ownership cannot be established over one or several sections without converting the whole immovableLaw No. 634, Art. 10/2

The first row is wider than most buyers expect. Article 14 of Law No. 634 frames the construction servitude as one created over land on which no building has been erected or whose building has not been completed; it is nevertheless a right entered in the land register, and Article 5 fixes how closely it is tied to the land share by forbidding that share to be transferred, inherited or encumbered separately from condominium ownership or from the construction servitude. A delayed permit therefore does not reduce the buyer to a possessor without title. What it does is freeze the character of the right at a servitude attached to a land share and postpone the moment when the unit appears in the register as an independent immovable. The security structure stays in the same place: a mortgage taken by a lender sits on the construction servitude until the conversion happens.

The registral entries deserve emphasis, because they explain why a delayed permit is felt years later. Article 10/6 of Law No. 634, as amended in 2021, makes both steps automatic once the permit exists: the class change of every building for which an occupancy permit is issued is carried out ex officio, the authority competent to issue the permit uploads it to the Spatial Address Registration System (Mekânsal Adres Kayıt Sistemi) and sends it electronically to the cadastre office, which prepares the registration notice from the permit and the building application project, the land registry records the change without seeking any further document, and where the immovable already carries a construction servitude, that servitude is converted into freehold condominium ownership ex officio on the basis of the original deed and the Article 12 documents, free of the revolving-fund service fee. Article 3/3 adds that a single land owner, or any one of the co-owners holding a construction servitude, can trigger the conversion. The whole machine is built to run by itself. The permit is the switch.

Can a flat without an occupancy permit get electricity and water?

Article 31 is the provision most often quoted and most often quoted incompletely. It provides that buildings for which a use permit has not been granted and has not been obtained are not supplied with electricity, water and sewerage services and installations until the permit is obtained. The next sentence, in the same article, then provides that independent units which have obtained the use permit are supplied with those services.

A closed barrier cuts off the road to an apartment building, with a light bulb beside it.
The rule on electricity, water and sewerage connections without an occupancy permit.

That exception is the practical route out for an individual apartment. Read with Article 30’s rule that finished parts capable of separate use may be permitted separately, it means the question to put to the municipality is not “when will the block be signed off” but “can this unit be signed off now”. A partial permit for the completed section restores that unit’s subscriptions even while the rest of the site remains open.

A separate, temporary route sits in Provisional Article 11 of Law No. 3194, added in 2008 and amended by Law No. 7417 in 2022. For a building that was erected in conformity with a construction permit obtained by 1 July 2022 but has no occupancy permit, water and/or electricity may be connected temporarily on application, within the subscriber group defined for it, where it is documented that one or more infrastructure services (road, electricity, water, telephone, sewerage, natural gas) have been brought to the building and the technical requirements of the relevant regulations are met. For buildings constructed before 31 December 2021 the condition of a construction permit and conformity with it does not apply. The connection creates no acquired right: if the municipality asks the distribution company to cut the electricity, the subscription is cancelled. Article 31 itself lists only electricity, water and sewerage; it does not mention natural gas or telephone lines.

One further gate is independent of zoning law altogether. Article 11/3 of Disaster Insurance Law No. 6305 requires the relevant undertaking to verify that compulsory earthquake insurance is in place when water and electricity subscriptions are made for buildings and independent units within the scheme, and Article 11/2 stops the land registry from carrying out registration or deletion transactions unless valid cover is evidenced at the date of the transaction. A buyer working through a stalled building therefore has two documents to track, not one.

Missing paperwork or an unlawful building?

This is the distinction that decides how serious the file is, and it is the one most often blurred in listings. The enforcement machinery is in Article 32, and it is triggered by construction started without a permit, or carried out contrary to the permit, its annexed studies and projects, or the zoning legislation. Where that is detected, the building is sealed and work stops immediately; since the 2020 amendment, the administration must notify the land registry in writing within seven days so that the non-conformity is recorded in the declarations column of the title register, and that record cannot be removed until the administration notifies that the breach has been cured. The owner then has one month to bring the building into conformity or obtain a permit; failing that, the construction permit is cancelled and the building is demolished by resolution of the municipal committee or the provincial administrative board, with the cost recovered from the owner.

None of that follows from a building that was constructed in accordance with its permit and whose owner simply never applied for sign-off. The administrative fines in Article 42 point the same way: they are imposed on buildings constructed without a permit or contrary to the permit and its annexed studies, projects and the zoning legislation. Occupation aggravates rather than creates liability, where the works are complete and the building is not in use the fine is increased by 10 per cent, and where it is complete and in use by 20 per cent. The lira figures in Article 42 are the nominal amounts in the enacted text and are increased each calendar year by the revaluation rate under repeated Article 298 of Tax Procedure Law No. 213, so any current figure must be taken from the year’s announcement rather than from the statute.

For a buyer, the practical test is therefore: read the declarations column of the title register first. An Article 32 annotation converts an administrative delay into a legal defect with a demolition file behind it, a materially different purchase from an unsigned-off but compliant block, and the point at which the general due-diligence sequence for foreign buyers needs to be widened rather than repeated. Where the permit or register extract shown by the seller does not match the municipality’s file, the issue is no longer zoning but the remedies covered in the note on real-estate fraud and title cancellation.

The Building Registration Certificate, and why it is not a route in

Provisional Article 16 of Law No. 3194, the 2018 zoning settlement, is still offered as a solution. As a fresh application it no longer exists: it required the building to have been constructed before 31 December 2017, the application to be made to the Ministry or an authorised body by 31 October 2018, and the registration fee to be paid by 31 December 2018.

What matters now is a certificate already in hand, and it does two things. First, buildings holding one may, on request, be connected temporarily to water, electricity and natural gas, taking into account the subscriber group defined for them in the relevant legislation, a discretionary and provisional connection, not the permanent supply that follows an occupancy permit. Second, and more significantly, the fifth paragraph allows the class change and the establishment of condominium ownership without an occupancy permit for buildings that took a construction permit but never obtained sign-off, and for buildings with no construction permit at all, on three cumulative conditions: the consent of all owners, the surrender of areas corresponding to public service zones on the zoning plan, and payment of twice the registration fee.

The limits are written into the article. The certificate is valid only until the building is rebuilt or an urban transformation scheme is applied, and current zoning legislation governs any renewal. The provision does not apply within the mapped Bosphorus shoreline and foreground zone, the mapped area of the İstanbul historic peninsula, or the Gallipoli Historic Area. And buildings standing on immovables owned privately by third parties are excluded from the article altogether.

When does a missing permit give the buyer a claim against the seller?

Where the shortfall was not disclosed, it is a legal defect and the standard warranty analysis applies to it. Article 219 of Turkish Code of Obligations No. 6098 makes the seller liable for material, legal or economic defects that destroy the value of the property for its intended use or materially reduce the benefits the buyer expected from it, and the following sentence states that the seller is liable even without knowing of them. Article 8/2 of Consumer Protection Law No. 6502 treats legal shortfalls the same way, and adds that a good is defective where it lacks features stated in advertising or on an internet portal, which is how a listing promising “iskânlı” delivery becomes contractual content.

The remedies are four in both regimes: rescission on declaring readiness to return the property, price reduction in proportion to the defect, free repair unless it requires excessive expense, and replacement with a defect-free equivalent where possible, with damages reserved under the general provisions (Article 227 of Law No. 6098; Article 11 of Law No. 6502). For a home, free repair or replacement must be delivered within sixty working days of the request under Article 11/4, the thirty-working-day figure belongs to movables. In practice the elected remedy for a stalled permit is usually price reduction or damages, because “repair” here means completing an administrative process the seller may not control.

On timing, Article 244/3 of Law No. 6098 gives five years from the transfer of ownership for claims arising from a building being defective, and twenty years where the seller is grossly at fault; Article 231’s general two-year rule is displaced. Where the defect is traced to the contractor’s work rather than the seller’s disclosure, Article 478 runs five years from delivery for immovable structures and twenty on gross fault, the sequence set out in the companion note on warranty and limitation periods for construction defects. For a consumer buying a home, Article 12 of Law No. 6502 gives five years from delivery and Article 12/3 disapplies limitation entirely where the defect was concealed by gross fault or fraud.

Two counterweights belong in the same paragraph. Article 10/1 of Law No. 6502 presumes that defects appearing within six months of delivery existed at delivery, unless the presumption is incompatible with the nature of the goods or of the defect. But Article 10/2 provides that there is no non-conformity where the buyer knew of the defect, or could be expected to have known of it, when the contract was made, so a purchase contract in which the buyer acknowledged the missing permit will be put in front of them. Where the claim proceeds, the forum and procedure questions are set out separately in the note on bringing a claim against a developer in the consumer courts, and the transactional side sits with our real estate law work.

The short version

The occupancy permit is a switch, not a wall. Turning it on releases the class change, the automatic conversion to freehold condominium ownership and the permanent utility connections, all of which the legislation is drafted to perform ex officio the moment the document exists. Leaving it off does not void the sale, does not by itself make the building unlawful, and does not necessarily cut a particular apartment off from electricity and water. What it does is hold the register in a provisional state that no individual owner can exit alone, and that is the reason to establish, before signing, exactly what stands between the building and Article 30.

Key figures

30 days
Statutory deadline for the administration to decide an occupancy-permit application (Art. 30)
7 days
Time to notify the land registry of a zoning non-conformity for the declarations column (Art. 32)
5 years
Limitation for claims arising from a building being defective (Art. 244/3, Law No. 6098)
2x
Multiple of the registration fee where condominium ownership is established on a Building Registration Certificate (Prov. Art. 16)

Checking the occupancy-permit position before you sign

  1. Read the register before the brochure

    Establish whether the title is a construction servitude (kat irtifakı) or freehold condominium ownership (kat mülkiyeti), and read the declarations column for any zoning non-conformity notified under Article 32 of Law No. 3194.

  2. Ask for the construction permit and its date

    Article 29 voids a permit where the building is not finished within five years counted with the two-year starting period, so an old permit may itself be the obstacle.

  3. Establish why sign-off has not happened

    A purely administrative delay and a physical deviation from the approved project are different problems: Article 30 requires conformity with the permit and its annexes before any permit can issue.

  4. Check the utility position unit by unit

    Article 31 withholds services from units without a permit but restores them for units that have one, and Article 11/3 of Law No. 6305 adds a separate compulsory earthquake insurance check at subscription.

  5. Put the position in the contract, in writing

    Record who applies for the permit, by when, at whose cost, and what happens if it does not arrive, and keep the correspondence, because Article 10/2 of Law No. 6502 removes the non-conformity where the buyer knew of the defect at the outset.

Frequently asked questions

Can I still buy an apartment in Türkiye if the building has no occupancy permit?

Yes. Nothing in Zoning Law No. 3194 or Condominium Law No. 634 prohibits the sale or the transfer of title where the occupancy permit is missing. What you acquire, however, is not the same thing. In a building that has not yet been signed off, the register normally carries a construction servitude (kat irtifakı) rather than freehold condominium ownership, because Article 14 of Law No. 634 establishes that servitude on land where no building has been erected or where the building has not been completed. It is entered in the land register and is tied to the land share: Article 5 of the same Law provides that where condominium ownership is transferred or passes by inheritance the land share attached to it passes with it, and that the land share may not be transferred, inherited or encumbered separately from condominium ownership or from the construction servitude, the two move together. Neither Law contains a provision prohibiting that transfer. The limitation is that the right stays a servitude over a land share until the permit arrives, and Article 10/2 of the same Law forbids converting one or two units alone: the ownership of the whole immovable must be converted, so a single buyer cannot cure the position for a single apartment.

What exactly does the occupancy permit unlock?

Three registral and administrative steps, in sequence. First, Article 10/6 of Law No. 634, as amended in 2021, provides that the class change (cins değişikliği) of every building for which an occupancy permit is issued is carried out ex officio: the authority competent to issue the permit uploads it to the Spatial Address Registration System (Mekânsal Adres Kayıt Sistemi) and sends it electronically to the cadastre office, which draws up the registration notice from the permit and the building application project, and the land registry records the change without requiring any further document. Second, where a construction servitude already exists on that immovable, it is converted ex officio into freehold condominium ownership on the basis of the original deed and the documents in Article 12, again without further paperwork, and these steps are exempt from the revolving-fund service fee. Third, Article 31 of Law No. 3194 permits the utility connections. Until the permit exists, none of the three can start.

Is it true that a flat with no occupancy permit gets no electricity or water at all?

Not as an absolute. Article 31 of Law No. 3194 says that buildings for which a use permit has not been granted and has not been obtained are not supplied with electricity, water and sewerage services and installations until the permit is obtained, and then adds, in the very next sentence, that independent units which do obtain the permit are supplied. The withholding therefore attaches to the unit's own permit status, not to the block as a whole, which is why a partial permit for completed sections under Article 30 has practical value. A second gate exists independently: Article 11/3 of Disaster Insurance Law No. 6305 requires the relevant undertaking to check that compulsory earthquake insurance is in place when water and electricity subscriptions are set up.

Does the missing permit mean the building is illegal and will be demolished?

No, and conflating the two is the most common error in this area. Sealing, the one-month cure period, the cancellation of the construction permit and demolition by resolution of the municipal committee or the provincial administrative board all sit in Article 32 of Law No. 3194, and Article 32 is triggered by construction started without a permit, or carried out contrary to the permit, its annexed studies and projects, or the zoning legislation. A building erected in conformity with its permit whose owner simply never applied for sign-off is not within that article. The distinction is visible in the register: since the 2020 amendment, Article 32 requires the administration to notify the land registry within seven days so that the non-conformity is recorded in the declarations column, and that entry cannot be removed until the administration notifies that the breach has been cured.

The developer says the permit is 'coming next month'. How do I test that?

By reading dates rather than assurances. Article 29 of Law No. 3194 gives two years from the date of the construction permit to start work, and provides that a permit is void if the building is not finished within five years counted with the starting period, whatever the reason, in which case a fresh permit is mandatory, with acquired rights on works already begun reserved. So the first question is whether the construction permit is still alive. The second is what stands between the building and sign-off: Article 30 conditions the permit on a finding that the building conforms to the permit and its annexes, which means a physical deviation must be cured before any application can succeed. The third is procedural: Article 30 obliges the administration to conclude an application within thirty days, failing which use of the building or of the completed part is deemed permitted.

Can the 2018 building amnesty still fix this?

Not by way of a new application. Provisional Article 16 of Law No. 3194 required the building to have been constructed before 31 December 2017, the application to be filed by 31 October 2018 and the registration fee to be paid by 31 December 2018. Those windows have closed. What still matters is a certificate already held: where a Building Registration Certificate (Yapı Kayıt Belgesi) exists, the fifth paragraph allows the class change and the establishment of condominium ownership without an occupancy permit, on three cumulative conditions, the consent of all owners, the surrender of areas falling within public service zones on the zoning plan, and payment of twice the registration fee. The certificate is also expressly stated to be valid only until the building is rebuilt or an urban transformation scheme is applied, and the provision does not apply at all in the listed Bosphorus shoreline and foreground zone, the İstanbul historic peninsula, or the Gallipoli Historic Area.

Do I have a claim against the seller, and how long do I have?

A missing permit that was not disclosed is a textbook legal defect. Article 219 of Law No. 6098 makes the seller liable for material, legal or economic defects that destroy the value of the property for its intended use or materially reduce the expected benefits, and states in the following sentence that the seller is liable even without knowing of them; Article 8/2 of Law No. 6502 counts legal shortfalls as defects in the same way. Article 227 gives four elective remedies, rescission, price reduction, free repair, replacement, with damages reserved. On timing, Article 244/3 of Law No. 6098 sets five years from the transfer of ownership for claims arising from a building being defective, and twenty years on the seller's gross fault; for a consumer buying a home, Article 12 of Law No. 6502 gives five years from delivery, and Article 12/3 disapplies limitation entirely where the defect was concealed by gross fault or fraud. The counterweight is Article 10/2 of Law No. 6502: there is no non-conformity where the buyer knew of the defect when the contract was made, so a clause in which you acknowledged the missing permit will be put to you.

How can I check whether a Turkish building has an occupancy permit?

Start with the land register. Article 12(a) of Condominium Law No. 634 requires the occupancy permit to be filed before freehold condominium ownership (kat mülkiyeti) is established, so a unit still registered as a construction servitude (kat irtifakı) usually signals that no permit has been filed; the exception is a building that moved to condominium ownership on a Building Registration Certificate under Provisional Article 16 of Zoning Law No. 3194, which allows this without an occupancy permit. Next, ask the municipality or governorate that issued the construction permit: under Article 30 of Law No. 3194 the same administration issues the occupancy permit and must decide an application within 30 days. Finally, read the declarations column of the title register, where a zoning non-conformity notified under Article 32 is recorded.

Can water or electricity be connected temporarily to a building without an occupancy permit?

Yes, within limits. Provisional Article 11 of Zoning Law No. 3194, as amended by Law No. 7417, allows a temporary water and/or electricity connection, on application and within the subscriber group defined for the building, where the building was erected in conformity with a construction permit obtained by 1 July 2022, at least one infrastructure service such as road, water, sewerage or natural gas has been brought to it, and the technical requirements are met. For buildings constructed before 31 December 2021 the construction-permit condition does not apply. The connection creates no acquired right, and the subscription is cancelled if the municipality asks the distribution company to cut the electricity.

This guide is general information, not legal advice. For advice on your specific situation, speak with a lawyer. Prepared by Lex Lata Consulting & Law.

Av. Onur Çalışıcı

About the author

Av. Onur Çalışıcı

Founding Attorney · Istanbul Bar Association · Bar reg. no 83426

Lex lata is Latin for “the law as it is”. The office was founded by Av. Onur Çalışıcı, and you deal with Av. Çalışıcı directly from the first meeting to the end of the matter. With foreign clients we write in English and explain what each Turkish document says.

Tell us briefly what happened and we will get back to you. This guide is general information, not advice on your case.

Last reviewed: October 2026 · LinkedIn: linkedin.com/in/onurcalisici

OfficeKarataş Sk. No:6, SNS Plaza Kat:3, Kağıthane, Istanbul

On screen

Beyaz TV · Beyaz Ana Haber · September 2026 · In Turkish

Evicting a tenant who disturbs the neighbours

Why a tenant's unbearable conduct has to be shown with concrete evidence, and the exceptional cases in which the 30-day period may not be required.

Related insights & legal guides

  1. Unlawful Occupation of Your Turkish Property: Two Separate Actions — Prevention of Interference and Ecrimisil
  2. Buying Property in Türkiye as a Foreigner: A Practical Guide
  3. Short-Term Tourist Rental Permits in Türkiye: The Unanimity Requirement and the Limits of the Management Plan (Law 7464)
  4. Asset Deal in Türkiye: The Debt That Transfers With the Business (TCO Art. 202, TCC Art. 11/3, Labour Act Art. 6)
  5. Inheriting Property in Turkey as a Canadian Heir: Applicable Law, Canadian Estate Papers and the Tapu Transfer
  6. Two Days, Eight Days or a Reasonable Time? Notice of Defect under TCC Art. 23(1)(c) and CISG Arts. 38–39
  7. Urban Transformation in Türkiye: What the 4 February 2026 Amendment Changed for Owners, and the Position of an Owner Who Does Not Sign
  8. Heirs in Germany and Property in Turkey: The 1929 Estate Rules, the Erbschein and the Turkish Certificate of Inheritance
  9. Reinstating a Struck-Off Turkish Company: The Action for Re-registration under TCC Art. 547
  10. Protecting Your Property Investment in Türkiye: The Complete Stage-by-Stage Guide

All guides

Practice areas

Office and events

Gürsel Mah., Karataş Sk. No:6, SNS Plaza Kat:3, Kağıthane / İstanbul · Address and directions

The Lex Lata office in Kağıthane, Istanbul: desks and wall screens showing the Lex Lata logo
The office · Kağıthane, Istanbul
Av. Onur Çalışıcı on the blockchain law panel at Blockchain Expo World, Istanbul, July 2024
Blockchain law panel · Blockchain Expo World, Istanbul · July 2024
A meeting around the table in the Lex Lata meeting room
Meeting room · Kağıthane, Istanbul

SNS Plaza, Kağıthane, IstanbulContact page